2018年8月13日月曜日

Sails in the Desert Refurbishment Announcement(エアーズロック セールス イン ザ デザート改装工事

Phase one: 25 January 2019 to 26 June 2019


Phase one of the refurbishment will occur in a staged manner, where small blocks of rooms will be taken out of inventory, with a “buffer block” allocated on each side to minimise guest impact.

Duration: 25th January 2019 to 26th June 2019
Hours of work: 7am to 5pm Monday to Friday and 7am-12pm Saturday
Noise: Some noise expected –no loud works permitted before 9:00am
Air pollution: None expected
Visibility of work: Limited. Majority of work to be completed inside rooms and away from guest view with site fencing/screen cloth as required
Flow of workers: Guided through back of house areas wherever possible, minimal impact to guests
Existing and new trade partner bookings: during this phase, minimal guest impact is expected, therefore new bookings will be accepted (subject to availability at time of booking) and existing bookings will be honoured.


Phase two: 4 November 2019 to 30 June 2020


Similar to Phase One, Phase Two will occur in a staged manner, where small blocks of rooms will be taken out of inventory, with a “buffer block” created to minimise guest impact.

Duration: 4th November 2019 to 30th June 2020
Hours of work: 7am to 5pm Monday to Friday and 7am-12pm Saturday
Noise: Some noise expected –no loud works permitted before 9:00am
Air pollution: None expected
Visibility of work: Limited. Majority of work to be completed inside rooms and away from guest view with site fencing/screen cloth as required
Flow of workers: Guided through back of house areas wherever possible, minimal impact to guests
Existing and new trade partner bookings: during this phase, minimal guest impact is expected, therefore new bookings will be accepted (subject to availability at time of booking) and existing bookings will be honoured.

0 件のコメント: